News 
 Local News 
 News 
 Political 
 State defends project delays - full statement 

State defends project delays - full statement

05 Jun, 2008 04:34 PM
A SPOKESMAN for the Infrastructure Department answers questions from the Bayside Bulletin on delays on local projects, as revealed in the updated South East Queensland Infrastructure Plan and Program.

1. Why have the completion dates for the road upgrades and Eastern Busway been pushed back; and why can’t the Cleveland rail corridor upgrades be delivered sooner?

The SEQ Infrastructure Plan has undergone a major review to keep pace with the changing needs of the region. The review involved a comprehensive analysis of the previous plan, integrated input from local government and industry, considered impacts of infrastructure delivery on industry and took account of other emerging issues to develop a strengthened plan for the region.

As part of the review the government has taken account of increased construction costs and implications from the current economic market into updated project estimated costs. These increased costs, combined with a range of new projects, have meant the program was re-sequenced to provide the best possible infrastructure program for the region as a whole, within affordability and capacity limits. As a result, some projects across the region have been deferred or re-staged within the program.

2. How will the road projects be staged?

Each project has funding allocated for planning and interim works to address safety and critical capacity upgrades in years 2008-2010. Details of early works have not yet been defined, they will be identified through 2008-09 planning. Anticipated staging profile for projects is as follows ($2008):

1. 4.17 Redland Sub Arterial Rd ($196M total)

- planning/early works ($35M) 2008-2010

- balance of construction in ($161M) 2018-19

2. 4.18 Cleveland-Redland Bay Rd Upgrade ($62M total)

- planning/early works ($22M) 2008-2010

- balance of construction ($40M) in 2019-21

3. 4.19 Redland Bay Rd Upgrade ($73M total)

- planning/early works ($18M) 2008-2010

- balance of construction ($55M) in 2019-21.

3. Why have the costs increased for these road projects, particularly 4.17 which has risen from $160 million in 2006 to $196 million now; and why has the cost of the Eastern Busway increased by more than 400 per cent ?

The increases in the costs of the road projects are due to improved estimating processes, rising delivery costs, and indexation to current dollars.

The increase in the cost of the Eastern Busway is linked to both a rise in construction costs across the board, as well as a re-scoping of the project.

* Looking specifically at cost estimates: many projects in previous editions of the plan have been in the very initial planning stages. The more planning and design work we undertake on various projects, the greater the certainty in costing estimates. This new version of the plan attempts to address this issue by adopting a 5-point scale for cost estimates. The scale varies by the level of planning done for a project – indicating the level of refinement required on the project costing.

* Looking at rising delivery costs: we should keep in mind that are currently in a significant gear-up phase in our infrastructure planning process. We have tripled our activity over the past few years. Combine this with the national - and in some cases international - boom in infrastructure delivery and these are challenging economic times. We face significant costs rises in material, labour, plant and professional services.

- Current tender box experience and independent reviews conducted by Main Roads and Australian Government indicate that increased construction costs (labour and materials) plus higher land acquisition and planning and design costs have led to average project cost escalations of 15% to 20% in recent years.

- Typical price increases for construction inputs on SEQ Main Roads projects over the past two years include:

General labour up 57%

Road base (supply only) up 69%

Bitumen up 40%

Steel fixing (assembly) up 83%

Diesel fuel up 50%

* Looking at indexation: we should note that projects in the initial planning phase (those with cost category 0 or 1 – around half the projects) have been indexed to 2008 dollars (using an factor of 4.4 per cent as advised by Queensland Treasury).

* Looking at Eastern Busway scope changes: the scope has expanded after public consultation resulting in a revised concept and design plan and there are now significant sections in a new tunnel. There is also a new section from Buranda to Princess Alexandra Hospital added in 2008.

4. Item 4.42 is new: Redland bus priority measures ($130m) in the 2019-2026 period. What will these measures involve?

On-road bus priority measures including transit lanes, traffic cue jumps, additional stations.

5. Item 4.52 lists Cleveland rail corridor upgrades ($180m) for the 2019-2026 period. What does this involve - is it duplication of the line between Manly and Cleveland?

Cleveland Corridor: Manly to Thorneside Duplication

Cleveland Corridor: Ormiston to Cleveland Duplication

Cleveland Corridor: Birkdale to Wellington Pt Duplication.

Print
Increase Text Size
Decrease Text Size
Page:
1

RELATED COVERAGE

comments


No comments yet. Be the first to comment below.

post a comment


Screen name  *
Email address  *
Remember me?
Comment  *
 
We invite and encourage our readers to post comments. Comments are moderated and will appear as soon as our editor has approved them. When posting comments you agree to be bound by our Terms and Conditions.
Related Coverage
ARTICLES

Most popular articles

2010 Redland directory